How to calculate percentage of work completed in construction

The recognition of revenue on an ongoing basis depending on the stages of a project’s completion

What is the Percentage of Completion Method?

The percentage of completion method is a revenue recognition accounting concept that evaluates how to realize revenue periodically over a long-term project or contract. Revenue, expenses, and gross profit are recognized each period based on the percentage of work completed or costs incurred.

How to calculate percentage of work completed in construction

Understanding the Percentage of Completion Method

The percentage of completion method falls in line with IFRS 15, which indicates that revenue from performance obligations recognized over a period of time should be based on the percentage of completion. The method recognizes revenues and expenses in proportion to the completeness of the contracted project. It is commonly measured through the cost-to-cost method.

There are two conditions to use the percentage of completion method:

  1. Collections by the company must be reasonably assured.
  2. Costs and project completion must be reasonably estimated.

Journal Entries: Percentage of Completion Method

Journal entries for the percentage of completion method are as follows:

How to calculate percentage of work completed in construction

Cost-To-Cost Approach

In the cost-to-cost approach, the percentage of completion is based on the costs incurred to the estimated total cost to complete the project. Therefore, the equation for the cost-to-cost estimate of percentage completion is:

Percentage complete:

How to calculate percentage of work completed in construction

Revenue recognized:

How to calculate percentage of work completed in construction

An example is provided below to clarify the cost-to-cost approach.

Example of the Cost-To-Cost Approach

StrongBridges Ltd. was awarded a $20 million contract to build a bridge. The estimated time to complete the project is three (3) years, with an estimated cost of $15 million. Assuming that the cost estimates do not change, the project is expected to generate $5 million in profit. The following is a schedule on the project:

How to calculate percentage of work completed in construction

Notes:

  • Costs Incurred are the costs incurred to build the bridge as estimated by the company’s engineer.
  • Billings are the amount of money StrongBridges Ltd. billed for the construction of the bridge. Billings amount is set by the contract.
  • Cash Collected is the amount of money StrongBridges Ltd. received for the construction of the bridge. The variation in billings and cash collected is due to timing differences.
  • % Completed is determined by the percentage completion formula.

For the schedule above, revenues recognized under the percentage of completion method:

  • Year 2008: 33% completed. Revenue recognized = 33% x $20 million (contract price) = $6,600,000
  • Year 2009: 47% completed. Revenue recognized = 47% x $20 million (contract price) – $6.6 million (previously recognized) = $2,800,000
  • Year 2010: 100% completed. Revenue recognized = 100% x $20 million (contract price) – $6.6 million – $2.8 million (previously recognized) = $10,600,000

Total Revenue = $20,000,000

Costs recognized under the percentage of completion method:

  • Year 2008: $5,000,000
  • Year 2009: $2,000,000
  • Year 2010: $8,000,000

Total Cost = $15,000,000

Profit recognized under the percentage of completion method:

  • Year 2008: $6,600,000 – $5,000,000 = $1,600,000
  • Year 2009: $2,800,000 – $2,000,000 = $800,000
  • Year 2010: $10,600,000 – $8,000,000 = $2,600,000

Gross Profit = $5,000,000

Journal entries for the example above would be as follows:

How to calculate percentage of work completed in construction

Thank you for reading CFI’s guide to the Percentage of Completion Method. To keep learning and developing your knowledge of financial analysis, we highly recommend the additional CFI resources below:

  • Evaluation Plan
  • Project Budget Template
  • Project Finance
  • Raid Log

How do you find the percentage of a completed work?

Task percent complete.
For the average, it is calculated by dividing the number of the completed work segments by the total number of segments in the work (tasks completed / total # of tasks)..
For time-based calculations, it divides the number of work hours completed / number of total work hours required for the segment..

How do you calculate project POC?

The Percentage of completion formula is very simple. First, take an estimated percentage of how close the project is to being completed by taking the cost to date for the project over the total estimated cost. Then multiply the percentage calculated by the total project revenue to compute revenue for the period.

What is POC construction?

What is the POC? The Path of Construction is the sequencing of the optimum building of the physical scope of the facility. In AWP terms, the POC is the sequence of your construction delivery in terms of the sequencing of your Construction Work Areas (CWAs) and Construction Work Packages (CWPs).

What is POC in project accounting?

The percentage-of-completion method (PoC) is a common revenue recognition method for companies that deal in long-term contracts.